// Record #15 — facility disclosure
Fluidstack France 1GW AI supercomputer: cancelled
8 Apr 2026 · France
// Facts, as published
- Facility status
- cancelled
- Total power (MW)
- 1,000
- Power, as published
- 1GW
- Power qualifier
- planned
// Curator note
MoU Feb 2025 (€10bn phase 1); withdrawal reported April 2026. Site never confirmed, so no coordinates.
// Parties
- operator
- Fluidstack GB
// Facilities
- subject
- Fluidstack France 1GW AI supercomputer FR
// Evidence
Archived primary
capture #1801 · 22 Oct 2026 · HTTP 200 · sha256 6a00ffc2d4f25a1ee7d5a4920e0f5b9aceaeb580975b3962b8c08dd0632e3395
// Version history
| Version | Status | Grade | Rights | Recorded | Reason |
|---|---|---|---|---|---|
| v1 | draft | C | pending_review | 22 Oct 2026 | created |